By using this site, you agree to the Privacy Policy and Terms of Use.
Accept
Kashmir DigitsKashmir Digits
  • KASHMIR
  • JAMMU
  • EDUCATION
  • INDIA
  • Results
  • TECHNOLOGY
  • Admit Card
  • EDITORIAL
  • HEALTH
  • JAMMU
  • JKBOSE
  • JOBS
  • Kashmir University
  • PAKISTAN
  • SPORTS
  • SRINAGAR
  • SSC
  • VIDEOS
  • WORLD
  • Share Market Latest
Reading: Of 272 km Udhampur-Baramulla rail link, 161 km already commissioned: Union Minister in Lok Sabha
Share
Notification Show More
Font ResizerAa
Kashmir DigitsKashmir Digits
Font ResizerAa
  • KASHMIR
  • JAMMU
  • EDUCATION
  • INDIA
  • Results
  • TECHNOLOGY
  • Admit Card
  • EDITORIAL
  • HEALTH
  • JAMMU
  • JKBOSE
  • JOBS
  • Kashmir University
  • PAKISTAN
  • SPORTS
  • SRINAGAR
  • SSC
  • VIDEOS
  • WORLD
  • Share Market Latest
  • KASHMIR
  • JAMMU
  • EDUCATION
  • INDIA
  • Results
  • TECHNOLOGY
  • Admit Card
  • EDITORIAL
  • HEALTH
  • JAMMU
  • JKBOSE
  • JOBS
  • Kashmir University
  • PAKISTAN
  • SPORTS
  • SRINAGAR
  • SSC
  • VIDEOS
  • WORLD
  • Share Market Latest
Have an existing account? Sign In
Follow US
  • Advertise
  • Advertise
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
INDIAJAMMUKASHMIR

Of 272 km Udhampur-Baramulla rail link, 161 km already commissioned: Union Minister in Lok Sabha

Sherjeel Malik
Last updated: March 29, 2023 4:17 pm
Sherjeel Malik
3 years ago
Share

The Centre on Wednesday said out of the total 272 km Udhampur-Srinagar-Baramulla rail link, 161 km has already been commissioned, while Rs 26,786 Crore expenditure has been incurred till March 2022 out of the anticipated cost of Rs 37,012 Crore.

In a written reply to a question in the Lok Sabha, Union Railways Minister, Ashwini Vaishnaw, as per the news agency—Kashmir News Observer (KNO) said that 272 km Udhampur-Srinagar-Baramulla Rail link (USBRL) project was sanctioned in 1994-95.

He said the anticipated cost of the project is Rs 37,012/- crore, against which, expenditure of Rs 26,786 crore has been incurred up to March, 2022 on the project.

“Out of the total 272 km length of USBRL project, length of 161 Km has already been commissioned. Work on balance stretch of Katra-Banihal section of 111 Km has been taken up,” he said.

He also said the completion of any Railway projects depends on various factors like quick land acquisition by State Government, forest clearance by officials of forest department, deposition of cost by State Government in Cost sharing projects, shifting of infringing utilities, statutory clearances from various authorities, geological and topographical conditions of area, law and order situation in the area of projects site, number of working months in a year for particular project site due to climatic considerations etc. “All these factors affect the completion time of the projects.”

On whether the government is likely to increase the number of trains
deployed to Kashmir with the completion of USBRL project, he said at present, 19 passenger special train services are running on Baramulla-Budgam-Banihal section of USBRL Project. Moreover, introduction of new train services or extension of existing train services is an ongoing process over Indian Railways subject to traffic demand, operational feasibility and availability of rolling stock.

Install Our AppDOWNLOAD
Join Telegram ChannelJOIN NOW
Join Facebook GroupJOIN NOW
Subscribe YouTube ChannelSUBSCRIBE
Follow On TwitterFOLLOW
Follow On InstagramFOLLOW

On whether the government is proposing to provide transport linkages to tourist destinations nearby the USB rail link, the minister said the new line projects are considered on the basis of demands raised by State Governments, Central Ministries, Member of Parliament, other public representatives and Railways’ own requirements. “As receipt of such proposals is a continuous and ongoing process, centralized compendium of such requests is not maintained.”

He added the proposals are taken up on the basis of remunerativeness, last mile connectivity, augmentation of congested/saturated lines, socioeconomic considerations, missing links and alternate routes including connectivity to tourist destinations etc., depending upon liabilities of ongoing projects, overall availability of funds and competing demands which is a continuous and ongoing process.

Share This Article
Facebook Whatsapp Whatsapp Telegram Email Copy Link Print
BySherjeel Malik
Follow:
Sherjeel Malik is a content writer at Kashmir Digits. Apart from covering current affairs, Sherjeel likes to create content about sports and write opinion based articles.
Previous Article Revision of electoral rolls doesn’t disturb schedule/conduct of polls: ECI Kashmirdigits Revision of electoral rolls doesn’t disturb schedule/conduct of polls: ECI
Next Article J&K saw nearly 15% economic growth and record tourist visits last year: LG Sinha Kashmirdigits J&K saw nearly 15% economic growth and record tourist visits last year: LG Sinha

Latest

JKBOSE Class 10th Result in January 2026
EDUCATION
J&K Minimum Temperatures Recorded Today
JAMMU KASHMIR
JK Minimum Temperatures Recorded Today
JAMMU KASHMIR
J&K Minimum Temperatures Recorded Today
JAMMU KASHMIR
JK Police Constable Admit Card Download Direct Link
JAMMU KASHMIR
J&K Bank
J&K Bank Recruitment
JAMMU JOBS KASHMIR
Winter Vacations Announced in Kashmir
KASHMIR
GMC-Jammu Kashmirdigits
GMC Jammu Last Date Extended
JAMMU
Winter vacation upto 8th standard from first week of December: Sakina Itoo
EDUCATION
Power Shutdown Notified for Kashmir Parts Kashmirdigits
JK Power Shutdown Schedule for 20th To 22 Nov 2025
JAMMU KASHMIR

Kashmir Digits Magazine is dedicated to the perpetuation of a free press for Students, Aspirants and independent Organisation as the cornerstone of our mission and movement here at Kashmir Digits.

Find Us on Socials

2025 © Kashmir Digits Media Network. All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?